Dear Valeud Customer,

In order to accommodate the continued growth and customer traffic demands within our data center, Network Engineers will be performing a maintenance to augment capacity between the master backend routers (MBR) and the data center aggregation routers (DAR). 


Start Date: Friday 27-Apr-2018 23:00 UTC
End Date: Sunday 
06-May-2018 14:00 UTC
Duration: 7 Days

Start Date: 06-May-2018 14:00 UTC
End Date: Sunday 
06-May-2018 14:00 UTC
Duration: 6 Hours

While this maintenance window is scheduled for 7 days, the actual network changes are only anticipated to take a few minutes per router. During this maintenance, new additional network links are being added to the routers and customer traffic shifted over to them in a graceful fashion. Therefore, the work is designed such that no customer disruption is anticipated. Customer applications which are highly sensitive to sub-second variations in latency may experience a very brief impact as the traffic shifts occur.

NO downtime is expected.

We appreciate your patience during this work and welcome any feedback.


Regards
Technical Support Department


Comments (0)
Post a new comment
 
 
Full Name:
Email:
Comments:
CAPTCHA Verification 
 
Please enter the text you see in the image into the textbox below (we use this to prevent automated submissions).

Help Desk Software by Hybrid Solutions